Current Schedule
I'll try to keep this list up-to-date as I receive information. This should give our neighbors an idea of what to expect in the coming months. Due to the nature of construction, though, all dates are subject to change.
January |
- Site prep (DONE)
- New 1" water line attached to city mains (DONE)
|
February |
- 8000 gallon water catchment tank installation (DONE)
- Prep and bury the catchment tank (DONE)
- Foundation prep and setting up concrete forms (DONE)
|
March |
- Foundation prep and concrete forms (DONE and passed inspection)
- Pouring concrete (DONE)
- Pop the forms (DONE)
- Back fill the foundations - (DONE)
- Framing the sub floor (DONE)
- March 23 - Start the underfloor plumbing and HVAC (DONE)
|
April |
- April 1 - Begin framing (DONE)
- April 3 - Frame the downstairs (DONE)
- April 14 - Initial electrical work (DONE)
- April 20 - Frame the upstairs (DONE)
- April 28 - Install the roof sheating (DONE)
|
May |
- May 12 - Install drops and soffits (DONE)
- May 12 - Begin rough plumbing and HVAC work (DONE)
- May 18 - More interior carpentry and pony walls (DONE)
- May 22 - Target inspection date for exterior shear work (DONE - PASSED)
|
June |
- June 5 - Rough interior carpentry (DONE)
- June 10 - Finish rough HVAC, plumbing, and electrical work (DONE)
- June 12 - Back yard deck framed (DONE)
- June 26 - Upstairs drywall loaded into rooms for weight factor (DONE)
- June 29 - Roof tiles loaded onto roof for weight factor (DONE)
- June 30 - Window installation begins (DONE)
|
July |
- July 8 - Rough frame, electrical, HVAC, and plumbing inspection (PASSED)
- July 9 - Install insulation (DONE)
- July 17 - Pickup framing and electrical (DONE)
- July 23 - Start installing the siding (DONE)
- July 27 - Drywall installation begins (DONE)
|
August |
- Aug 5 - Initial interior painting (DONE)
- Aug 10 - Cabinet installation (DONE)
|
September |
- Early September - Tile prep (DONE)
- September 28 - Interior doors (DONE)
- September 30 - Garage door (DONE)
- Tile work started (DONE)
- Interior trim carpentry - first pass (DONE)
- Exterior painting - first coat (DONE)
|
| October |
- October 13 - Interior painting - first coat (DONE)
- October 14 - Countertops (DONE, but needs fixing)
- October 15 - Roof tile install (DONE)
- October 19 - More plumbing (DONE)
- October 19 - Tile work continues (DONE)
|
| November |
- November 2 - Begin final plumbing (DONE)
- November 4 - Begin final electrical (DONE)
- November 11 - Install wood floors (DONE)
- November 23 - Dig trench for PGE (DONE)
|
| December |
- December 5-6 - Install stair treads
- December 7- Finish front porch
- December 7 - Finish upstairs deck
- December 7 - Final plumbing
- December 8 - Install carpet and linoleum
- December 8-10 - Finish hardwood floors
- December 11 - Baseboard and trim
- December 11 - PGE hookups ???
- December 14 - Finish cabinets and install drawer pulls
- December 14 - Install driveway pavers
- December 14 - Install back deck
- December 14 - Install shower glass
- December 14 - Install appliances
- December 14 - Final electrical
- December 18 - Final inspection
- December 21 - Move in
|